Pumped-storage hydro · grid battery
Limberg III
operatingAustria · lower reservoir on the Kapruner Ache
- Turbine capacity
- 480 MW
- Energy storage
- -
- Gross head
- -
- First unit
- 2025
Opened September 2025 on the same reservoir pair as Limberg II; both motor-generators failed within weeks, with repaired sets due back in September and December 2026
Nameplate figures and coordinates: Verbund press release · 47.1985, 12.7205